Verifying the SAN Volume Controller installation Installing Installation overview for the svcc

After you have installed the SAN Volume Controller into the rack and connected it to both the uninterruptible power supply and the SAN, this task provides the steps you complete to verify the installation.

Prerequisites

Check the configuration data table provided by the customer the speed at which the SAN Volume Controller nodes are to be operated (usually 2 Gbps).

Steps

Perform the following steps to verify the installation of the SAN Volume Controller.

  1. Press the SAN Volume Controller power switch. Verify that the green power light is on. If the light is not on go to MAP 5000: Start to repair the problem.
    Note:Note: You do not need to install any software. The node boots automatically.

    Verify that the node is booting without error:

    • If it boots without error, the Charging message is displayed in line 1 of the front panel display. A progress bar is displayed in line 2 of the front panel display. Battery charging can take up to 3 hours until the battery is fully charged. When the battery is charged enough, Cluster: is displayed in line 1 of the front panel display; line 2 is blank.
  2. Press and hold the select button for five seconds. The check light comes on and a display test is performed. When the display test is complete the check light goes off and a button test is started.
  3. Press the up, down, left, and right buttons to verify that they are working. See Figure 57, which shows four examples of what the front panel should display when you press the buttons. When you have finished testing the buttons, press and hold the select button for five seconds to exit the test.
    Figure 57. Front panel display when push buttons pressed
    Front panel display when push buttons pressed
  4. If the Charging message is displayed on the front panel display, press the select button to switch to the menu. The menu continues to be displayed while you press the buttons on the front panel. If you do not press any buttons within 60 seconds, the menu changes to display the charging progress. You can switch the front panel display to the menu at any time by pressing the select button again.
  5. Keep pressing and releasing the up or down button until the Node: option is displayed in line 1 of the front panel display.
  6. Verify that the node number that is displayed in line 2 of the display is the same as the node number that is printed on the front panel of the node (see Figure 58).
    Figure 58. Node number
    svc_displaynode_23NLFh.eps
    The XXXXXX in Figure 58 represents the node number. If the numbers do not match, exchange the Front Panel FRU on the SAN Volume Controller.
  7. Keep pressing and releasing the up or down button until the Ethernet option is shown on the front panel display. Line 2 of the front panel display shows the message Inactive. This message shows that, although an Ethernet connection is available, it cannot yet be used (see Figure 59).
    Figure 59. Ethernet mode
    svc_displayethernetinactive_1nnh7k.eps
  8. Keep pressing and releasing the up or down button until the FC Port-1 option shows in the display.
  9. Check whether line 2 of the display shows the message Active.
  10. Keep pressing and releasing the left or right button to display the other port options. Check whether for each port, line 2 of the display shows the message Active. If Active is not shown for any port, go to MAP 5600: Fibre-channel to repair the fault.
  11. If the configuration data table provided by the customer indicates that the SAN Volume Controller nodes are to be operated at 1 Gbps, press and hold the down button; press and release the select button. Release the down button. The second line of the display will show the current fibre channel speed setting of the node. Press the up or down button until 1 Gbps is displayed and then press the select button. This changes the fibre channel speed for all ports on this node to 1 Gbps.
  12. If you want to select a language other than English, perform the following steps:
    1. Press the up or down button until Select Language? displays.
    2. Press the select button.
    3. Press the left or right button until the required language is displayed.
    4. Press the select button.
  13. Repeat steps 1 through 12 for each SAN Volume Controller.
  14. When the battery is fully charged, the charge progress bar is replaced by the Cluster option on the front panel display of the SAN Volume Controller.

You have completed the hardware installation for the SAN Volume Controller. The customer can now begin to create clusters and perform other configuration tasks. See the IBM TotalStorage SAN Volume Controller: Configuration Guide for detailed configuration instructions.