Before you start to install the uninterruptible power supply and the SAN Volume Controller, ensure that you have everything that you need, including the customer completed planning tables and charts provided in the IBM TotalStorage SAN Volume Controller: Planning Guide. These tables include the location of hardware, cable connection, and configuration data information that you will need to complete the installation procedures.
Perform the following steps:
| 1 | SAN Volume Controller | 4 | Uninterruptible power supply rail kit |
| 2 | SAN Volume Controller support rails (2) | 5 | Power and signal cable |
| 3 | Uninterruptible power supply (2) |

| Note: If you are installing the SAN Volume Controller into a rack that already contains other SAN Volume Controller and uninterruptible power supplies, the installed uninterruptible power supplies might have spare capacity. If the customer intends to use that spare capacity, the SAN Volume Controller that you are going to install might have been delivered without uninterruptible power supplies. |