Before you can install the uninterruptible power supply, you must install the support rails into the rack.
| Note: If you are installing the SAN Volume Controller into a rack that already contains other SAN Volume Controllers and uninterruptible power supply, the installed uninterruptible power supply might have spare capacity. If the customer intends to use that spare capacity, the SAN Volume Controllers that you are going to install might have been delivered without uninterruptible power supply. |
Perform the following steps to install the support rails for the uninterruptible power supply:
| Note: The bottom of the flange of the support rail must align with the EIA mark on the rack. |

| Attention: To tighten wing nuts 2 and 3 you will require access from above the rails. Ensure that the support rails are installed before anything is installed in the 8 EIA units above the rails. If any pre-existing devices have been installed in that space it might be necessary to remove those devices before installing the rails. |
| Note: Hold the support rail in position until you have completed step 4h. |